Quote Date | 2 Jan 2021 |
Quote Number | RIN/FWC/018/20-21 |
This is SAMPLE QUOTE, we will provide exact quote based on floor plan, structural design and site conditions and material rates at the time of order confirmation.
Rincon Realty Pvt Ltd | |||||
---|---|---|---|---|---|
Client - Name | Date: <<- date ->> | ||||
SL.NO. | DESCRIPTION | UNIT | QTY | Rate | Amount |
1 | Ground Floor | ||||
Built Up Area | Sft | 736 | ₹1,495 | ₹1,100,320 | |
Car Park@70%(total area 276 sft ) | Sft | 193 | ₹1,495 | ₹288,834 | |
2 | First Floor | ||||
Built Up Area | Sft | 407 | ₹1,495 | ₹608,376 | |
Parapet Wall 3.5 feet | Sft | 245 | ₹295 | ₹72,275 | |
3 | Extra items | ||||
UG Water Tank | Litres | 6,000 | ₹18 | ₹108,000 | |
Septic tank | Litres | 6,000 | ₹18 | ₹108,000 | |
Overhead (Sintex type) | Litres | 3,000 | ₹5 | ₹15,000 | |
RCC Compound wall - 5 feet height | feet | 650 | ₹195 | ₹126,750 | |
Gate 5 feet height (30 X 40 feet Plot) | Sft | 50 | ₹313 | ₹15,625 | |
Sub Total "A" | ₹2,443,180 | ||||
4 | Design Charges | ||||
Architecture, Structural design & drawings | Sft | 1,143 | ₹35 | ₹40,003 | |
Sub Total "B" | ₹40,003 | ||||
TOTAL A + B | ₹2,483,182 |
Material rate assumption | ||
---|---|---|
Sl No | Description | Rate |
1.1 | Cement | ₹360 |
1.2 | Steel | ₹53 |
1.3 | Sand | ₹50 |
1.4 | Jally | ₹30 |
Note : | |||||
1 | The above quantities may vary based on site condition. | ||||
2 | Elevation works will be an additional cost based on the 3D drawing. | ||||
3 | The BOQ (Bill of Quantity) covers all the items and materials that are mentioned in the package. Anything not mentioned in the package but opted by the client will be at an additional cost. | ||||
4 | Above charges are exclusive of applicable taxes. |
Materials Make & Brand List | ||
---|---|---|
Sl No | Description of item | Brand |
1 | Cement opc 43 and 53 grade | Chettinad or equivalent |
2 | Reinforcement Steel | ARS, Mangal Steel or equivalent |
3 | Sand | M-sand |
4 | 20 mm Coarse aggregates | As per local availability |
5 | 40 mm Coarse aggregates | As per local availability |
6 | Vitrified tiles | Budget Rs. 40/sft |
7 | Ceramic tiles | Budget Rs. 40/sft |
8 | Anti skid | Budget Rs. 40/sft |
9 | Sanitaryware and CP (taps) | Parryware basic (max. ₹8,000) |
10 | Paint | Asian Paints (basic) |
11 | Electrical items | Finolex, Anchor |
12 | Waterproofing Chemical | Dr. Fixit, Fosroc |
13 | Aluminium Windows | Best available in market @200/sft |
14 | Door shutter and frames | Main door: moulded skin door. Flush doors for rooms. Bathroom door - PVC. Concrete frame or mahogany. |
Work & Payment Schedule | ||
---|---|---|
Date | Stage - starting | Payment |
Design - floor plan | ₹25,000 | |
Start Foundation | ₹450,000 | |
Start GF Wall & Slab | ₹550,000 | |
Finishing works part 1 | ₹400,000 | |
Start FF Wall & Slab | ₹400,000 | |
Start finishing works part 2 | ₹250,000 | |
Handover | ₹408,182 | |
Total | ₹2,483,182 |
Web | http://RinconRealty.in |
Phone | Sumeet @ 97909 64110 |
sg@rinconrealty.in |