Shear Wall Sample Quotation
Rincon Realty Nov 2020
A | B | C | D | E | F | G | H | I | J | K | L | |
---|---|---|---|---|---|---|---|---|---|---|---|---|
1 | Quote Date | <<date>> | This is SAMPLE QUOTE, we will provide exact quote based on floor plan, structural design and site conditions and material rates at the time of order confirmation. | |||||||||
2 | Quote Number | RIN/FWC/018/20-21 | ||||||||||
3 | ||||||||||||
4 | Rincon Realty Pvt Ltd | Materials Make and Brand List | ||||||||||
5 | Client – Name | Date: <<date>> | Sl No | Description of item | Brand | |||||||
6 | SL.NO. | DESCRIPTION | UNIT | QTY | Rate | Amount | 1 | Cement opc 43 and 53 grade | Chettinad or equivalent | |||
7 | 1 | Ground Floor as per the Drawing | 2 | Reinforcement Steel | ARS, Mangal Steel or equivalent | |||||||
8 | Built Up Area | Sft | 736 | ₹1,495 | ₹1,100,320 | 3 | Sand | M-sand | ||||
9 | 4 | 20 mm Coarse aggregates | As per local availability | |||||||||
10 | 2 | First Floor as per Drawing | 5 | 40 mm Coarse aggregates | As per local availability | |||||||
11 | Built Up Area | Sft | 407 | ₹1,495 | ₹608,376 | 6 | Vitrified tiles | Budget Rs. 40/sft | ||||
12 | Parapet Wall 3.5 feet | Sft | 245 | ₹300 | ₹73,500 | 7 | Ceramic tiles | Budget Rs. 40/sft | ||||
13 | ₹681,876 | 8 | Anti skid | Budget Rs. 40/sft | ||||||||
14 | 9 | Sanitaryware and CP (taps) | Parryware basic (max. ₹8,000) | |||||||||
15 | Sub Total Amount | ₹1,782,196 | 10 | Paint | Asian Paints (basic) | |||||||
16 | TOTAL A | ₹1,782,196 | 11 | Plywood 12mm, 18mm, 24mm | Budget Rs. 55 | |||||||
17 | 12 | Electrical items | Finolex, Anchor | |||||||||
18 | 3 | Design Charges | 13 | Laminate | TBD | |||||||
19 | Architecture, Structural design & drawings | Sft | 1,143 | ₹50 | ₹57,147 | 14 | Waterproofing Chemical | Dr. Fixit, Fosroc | ||||
20 | TOTAL B | ₹57,147 | 15 | Aluminium Windows | Best available in market @140/sft | |||||||
21 | 16 | Door shutter and frames | Main door: moulded skin door. Flush doors for rooms. Bathroom door – PVC. Concrete frame or mahogany. | |||||||||
22 | TOTAL A + B | ₹1,839,343 | ||||||||||
23 | ||||||||||||
24 | Note : | The above quantities may vary as per site condition. | Work & Payment Schedule | |||||||||
25 | GST Extra | Date | Stage – starting | Payment | ||||||||
26 | Design – floor plan | ₹25,000 | ||||||||||
27 | Web | http://RinconRealty.in | Start Foundation | ₹450,000 | ||||||||
28 | Phone | Sumeet @ 97909 64110 | Start GF Wall & Slab | ₹550,000 | ||||||||
29 | sg@rinconrealty.in | Finishing works part 1 | ₹300,000 | |||||||||
30 | Start FF Wall & Slab | ₹350,000 | ||||||||||
31 | Start finishing works part 2 | ₹150,000 | ||||||||||
32 | Handover | ₹14,343 | ||||||||||
33 | Total | ₹1,839,343 |