Rincon Realty Pvt Ltd – Sample Quotation
SL.NO | DESCRIPTION | UNIT | QTY | Rate | Amount |
---|---|---|---|---|---|
1. | Ground Floor as per the drawing | ||||
Build Up Area (incl uncovered stair case) | Sft | 727 | ₹1,795 | ₹1,304,965 | |
Utility Area (Uncovered area) | Sft | 37 | ₹898 | ₹33,208 | |
Car Parking Area (Uncovered area) - area assumed, not clear in drawing | Sft | 200 | ₹898 | ₹179,500 | |
2 | First Floor as per the drawing | ||||
Build Up Area (EXCL stair case) | Sft | 424 | ₹1,795 | ₹761,080 | |
Car Parking Area (Uncovered area) - area assumed, not clear in drawing | Sft | 80 | ₹898 | ₹71,800 | |
NO Head Room | Sft | ||||
3 | Extra Work | ||||
Septic tank | Litres | 4,000 | ₹33 | ₹132,000 | |
RCC Underground water tank | Litres | 7,000 | ₹33 | ₹231,000 | |
Overhead water tank (plastic double wall) | Litres | 2,000 | ₹10 | ₹20,000 | |
RCC Compound Wall - 5ft height, 3" thk | Sft | 135 | ₹350 | ₹47,250 | |
Ramp, planter box | Extra | as per site conditions |
|||
Gate - 5 feet height (2.5 kg per sft) | Sft | 50 | 345 | ₹17,250 | |
Weathering course | Sft | ₹95 | ₹0 | ||
TOTAL | ₹2,798,053 |
Materials Make and Brand List
Sl No | Description of item | Brand |
---|---|---|
1 | Cement opc 43 and 53 grade | Priya or equivalent |
2 | Reinforcement Steel | ARS, Mangal Steel or equivalent |
3 | Sand | M-sand |
4 | 20 mm Coarse aggregates | As per local availability |
5 | 40 mm Coarse aggregates | As per local availability |
6 | Vitrified tiles | Budget Rs. 40/sft |
7 | Ceramic tiles | Budget Rs. 40/sft |
8 | Anti skid | Budget Rs. 40/sft |
9 | Sanitaryware and CP (taps) | Parryware (max. ₹12,000 per bathroom) |
10 | Paint | Asian Paints Interior: Tractor Emulsion Exterior: ACE |
11 | Electrical items | a. Wiring: Orbit or equivalent b. Switches: Anchor Roma c. Fittings (ligth,fans, etc.): Not included |
12 | Waterproofing Chemical | Dr. Fixit, Fosroc |
13 | Windows | Powder coated alumnium sliding Best available in market @ 200/sft |
14 | Door shutter and frames | Main door: moulded skin door. Flush doors for rooms. Bathroom door - PVC. Door frame: mahogany or equivalent |
15 | Car Parking Flooring Tiles | Budget Rs. 40/sft |
16 | Staricase & balcony handrail, grill | MS basic design |
Stage | Payment |
---|---|
Token Advance (2 weeks before start date) | ₹50,000 |
Start of Foundation (subtract token advance) | 30% |
Start of GF - wall & slab | 30% |
Start of FF - wall & slab | 20% |
Start of Finishing works | 20% |
Total | 100% |